Do you to revised shipment 22 by add Clear 500ml : 698bxs ?
Old shipment 22 had preform 500 ml 474,050/499 but you revised shipment 22 by add Clear 500ml : 663,100/698.
So,after revised from the preform planner confirm on 8/4 and for preform 500 ml in next shipment had delay two days from old day .
If you don’t revised you will used old confirm schedule.
Please review and confirm by return.