Dear: All
Tomorrow I decide to assign K Uthai contact to FKT Thai staff. To discuss about this material shortage issue. And inform honestly to them. Now ARC face supplier problem. They stop supply PVC material to ARC cause they cannot control. Then we find new source and we already get new material PVC and during this time we will face material shortage. And we will propose to FKT.
1. Can we sorting the Defect that we have in ARC2 and set limit that can be special (If possible)
2. And to propose new material and show them material spec compare old spec and new spec for special lot, during waiting for approve fro Kubota. (This is due to material supplier cannot control the quality of PVC material supply to ARC)
Any advise please give me the idea.
Current supplier is local take about 1 week order but now they out of stock. And new material we have to wait for 45 days