Please kindly see in attached file about plan ship out Jan 14. Thank you ka.
PO#4508442820 still wait thread and wait answer from supplier holiday 24-Dec to 3 Jan , they will resume to work on 04-Jan.
If supplier have thread in stock may be production line will delay one-two week. but if supplier not keep in stock for thread need lead time around 3 week ( That’s really bad. )
So, Production line will plan delay three weeks and they plan finish on 30-Jan by first. please kindly help inform reason this case to customer accept new finish date and ship out by sea.