The scope of works per to this FI shall include. but not limit to. the following
Supply of Materials
Tube fitting for connection between pipe and tubes (4 locations). fitting materials shall be 316 stainless steel (swegelok)
Supply of supports, insulation and painting (LC3N)
Pipes,elbows, bolts and nuts, gaskets will be supplied by TOP
Hastelloy tubes will be supplied by TOP
Detailed scope of Works.
1) Fabrication and installation of pipe as attached sheet herewith. Supports will be field run installation by Contractor
Contractor shall perform site check for dimensions before starting work
2) Provide NDE for piping 5% RT
3) Provide hydrostatic test at 27.74 barg for tubes is 1 barg. After hydrotest pipe and tube shall be clean by water flush and dry with air drain pipe to COC is not require presssure test
4) Provide and installation and jacketting for both pipes and tubes, insulation thickness is 2 inch
5) Provide equipment tools and scaffolding as necessary for fabrication and installation works
6) Repair the existing damage paint and insulation as concern
7) Remove tubes and tube bundle and return to Thai Oil Project Warehouse for spare
Note
- This instruction required in a urgently priority
- The final cost impact to these FI will be remeasure again against to the actual work done with together a statement showing the desciption and quantity of all Mat'l or construction equipmet
- For the Mat'l supplied the contractor shall provide copy of receipt/invoices to prove the amount paid