LOB is oriented toward the required delivery of completed units
and is based on knowledge of how many units must be completed
on any day so that the programmed delivery of units can be
achieved. Once a target rate of delivery has been established for
the project, the rate of production of each and every activity is
expected not to be less than this target rate of delivery ~Lumsden
1968!.