A. Observation
The process flow of curing department is received the
curing mould from lay-up department and allocate it at the
before cure area. The mould to be cured is being verified
and the paperwork is checked. Vacuum and thermocouple
are setting up on the mould after the verification. In the
loading process, bed is load into autoclave, vacuum hose
and thermocouple internal setting are to be done to connect
it to the autoclave. The operator is then chec ked the curing
recipe or profile form the system and enter the required
data to the autoclave curing system. After the data entry,
leak check to ensure that the vacuum hose and
thermocouple are functioning and prevent the operation
from unplanned shutdown hence performing specification
to make a good product. The autoclave door is closed and
the door ring is locked.