26 September 2016 - Issue PO and deposit payment by CS
27 September 2016 - Manufacture start by Hafele
5 November 2016 - Installation complete by Hafele
6 - 12 November 2016 - Installation finishes by CS
13 -16 November 2016 - Spare time for defect inspection and rectification
17 November 2016 - Handover
Should you have any question please let me know.