The ideal plan for us is to do full semi-annual inspection during the upcoming shutdown schedule 00:00 1 Feb ~ 24:00 2 Feb
(we confirm that the shutdown is allowed from 00:00 on 1 Feb ~ 24:00 2 Feb.) and plug in compressor water washing schedule.
But it seems quite tight. Could you kindly send us the full semi-annual inspection schedule on hourly basis so that we can
understand if all works can be done within the original timeline?