Refer attached email from Nissan where they are asking for delay of JQTA for L12F (year2) ASR, GCC, THI SOP.
This is currently planned for 13/April.
As per below email, the CKT MRD is 15/May. Based on this date, when the SW needs to be released to plant to meet MRD?
Is there any change in MRD?