We'll discuss and decide which of the 5L bags to order.
We still have 5L foil bags samples. Are you providing us the metalized bags sample?
How many are you allocating? Provide me the dimension of the packing for the samples and I can arrange them to collect.
As for the delay in commissioning, details as follows:
Machine received in December 2014.
1st commissioning in early Jan 2015 and was delayed till 3rd commissioning in April. Due to missing parts from Auckland and lack of precise information for the pipeline facilities.
It took 4 months to complete the commissioning and yet the result was not as expected. There are bags sealed with some wrinkles & back folding and leaking products were found after fine tuning (the most recent one in August 2015). However, we decided not to claim any of the opportunity cost here.
We're just looking forward a better and improved business relation with Rapak. Kindly quote us the best price possible for both the 5L and 20L bags.
The price will be one of the decision factor aside from standardizing the material of bags to be used.