Hi Khun Suwat, Khun Nattapong,
This is to updating you about our action plan and time line:
1) As mentioned, the nozzles will only be arrive earlier mid/end of next week.
2) We will organize Mr Pannawat to be on site 1st August 2016 and once the nozzles arrive he will be able to fix it.
3) For further support, if Mr Pannawat have any issue and problem on site we will get him the closest support in the area
4) For the exit ramp issue, we are working on it in our engineering department once we have further news or proposal then we will share with you immediately.
For further information, please feel free to call my mobile: +65-8399-0463
Once again we apology for any inconveniences