Single Item MRP is run for a single material in one plant and can be used for troubleshooting purposes.
It is not possible to run Single Item MRP for a group of materials.
After reviewing the results of Total Plant MRP, it is necessary to run Single Item MRP in order to troubleshoot any items that need to be corrected.
Single Item MRP is carried out by the MRP Controller.