Each Affected Party initiates its own change implementation process following approval of the change. For the incorporation into the plant design and construction, the Plant PMT will ensure that Contractors have incorporated the change technically and commercially by reviewing the appropriate drawings (e.g. P&IDs, layouts) and invoices. Plant Project Controls Manager will also notify Finance and Accounting of the change if it affects project cost or timing. Similar for the pipeline.