And in this station it was found that pneumatic torque
gun pipes get inter tangled with another stations pipes
as the point of pneumatic input to guns of different
station is common and 10 times approximately the pipe
gets inter tangled with the other pneumatic gun pipe
and workers cannot work when the pneumatic gun pips
are inter tangled, and around 15 seconds are spent just
to untangle the pipes and the time get wasted due to
inter tangle of the pneumatic pipes is around 150
seconds daily and total time wasted at this station
increases to (480 + 150)seconds= 630 seconds
minimum or around 10:50 minutes per day and
exhausted to labour also.