) 21.11.2015
Electrical power supply re-installed to ESP for running the Hopper Heaters , Insulator heaters, RAV, Collecting electrode rapping, discharge electrode rapping, GD Screen rapping. – 7 Hours.
Open circuit & Close Circuit test of TR Set – 2 Hours.
Air load charging of three fields by TR Sets – 3 hours.