Since the Wine keg is coming end of Sept, I’d talked with K.Somkiat for this launch delay in Makro.
Next step, pls urgently check step and lead time of ;
1. How many days local supplier need to process sticker at lid and bottom and label. ทยอยทำ ทยอยส่งโรงงานได้ไม๊
2. How many days of production process.
3. I’d talk with K.Somkiat to take order at last week of October, is it possible?
4. Prepare everything to be ready such as Carton, label Sticker/lid/bottom by end of August.
If necessary, pls call meeting with production team and purchasing.