7 December 1887: Construction of the legs with scaffolding.
20 March 1888: Completion of 1st level.
15 May 1888: Start of construction of second stage.
21 August 1888: Completion to 2nd level
26 December 1888: Construction of upper stage
15 March 1889: Construction of cupola