-Install the door already. Will install the door Pantry cabinet and install laminate sheet magnetic tomorrow, and will install the aluminum u chalnel and touch up all for 12/6/15, section and post form top and glass to install on 19/6/15 (wait).
-D-NET Install the power outlet and lighting then some and install again tomorrow. Grid suply air and the return air is installed in this week. Parts sprinklers, emergency lighting, cctv, access control is tracking K.best for that is installed
-KWC Cleaning tomorrow 13:00pm.
-Carpet delivery tomorrow and installation 12/6/15.