Changes are classified according to the impact of the change and the approval authority needed
Depending on the criticality, impact, and cost involved, there will be a hierarchy of people who can approve the changes
◦The top of the hierarchy is the change control board (CCB)
Major changes need the approval of the CCB
Minor changes can be done with the approval of the project manager or development manager