(ก) If Subcontractor does not complete the Work on or before, Subcontractor shall pay to Contractor, as liquidated damages and not as a penalty, 0.1% of the Contract Price for each Day delayed.
(ข) The sole liability of Subcontractor to Contractor remedy for the unexcused failure of Subcontractor to comply with the schedule undertaking provided herein.