Reference for our conversation on the phone this evening , please look the layout for the job at Carls house, and then explain to the electrician what he needs to do…
Attached are two drawings, please read email below. To summarize the electrician needs to provide and install the following things:
• Upgrade the existing house distribution board to 125amp
• Upgrade the existing transfer switch to 125amp
• Install a junction box near to the transfer switch. The junction box will connect the Generator to the Load Bank, before it connects to the transfer switch. The junction box should have a 3 pin,16amp blue socket, so we can plug the load bank into it.
• Upgrade power cable and Install 2Core+Gnd (35/10sqmm) as follows:
o House Distribution Board to the Transfer Switch
o Transfer Switch to the Junction Box
o Junction box to the Generator
• Install 2 metre Earth Rod and connect to the house distribution board with THW Ground Connector (10sqmm)
Please explain to Carls electrician what his scope of work has to be, what he needs to supply and install, so it’s all ready before we arrive… so important he gets this correct … if you doesn’t understand, please let us know and will try to explain again. Thank you.
this is the telephone number and email for you to give to call the electrician who will do the work at Carls house…
Chai (solar man) 0815590999
Or 0801832233