Focus your work on Medium Voltage Swtichgear,LV,DPs.etc.
Your work is behind schedule and should be improved.Focus your effort on making generator control system work.
If there is anything change in High Votlage Substation,you will be informed.
K.Somporn and K.Wisal will be in the team in case there is a decision change.
Don’t spend more time on this issue until instructed.
Thanks for your understanding.