we noted the existence of some issues with the facility infrastructure at the failover data center. Specifically, we noted the presence of water piping in the ceiling of the failover data enter. the water piping was present because this data center was created from office space originally intended to be occupied by personnel. at the time of construction, the water sprinkler heads were removed from the piping and the piping was capped. however, the piping remained and continued to be connected o the active water based pre-action fire suppression system of the building.