Khun Nettinai & Khun Tanyarat….
• We need to submit the revised Thermal report (with thermal report) based on Monday….
• One week has passed since I sent this email below….with no comment from anyone….!
• Are we on track? Are there any issues? All must communicate on a regular basis…(all emails to be responded or at least noted within weekly EQ meetings…)
Khun Tanyarat & khun Nettinai Hi…
Please review the prelim thermal report attached…
Please review and comment:
• I believe this is only the Winter condition?
• Also some errors within (ie: photo from other project, etc..)
• Review carefully…
ADDITIONAL NOTE/S
• Please try to follow this concept for next and all future thermal analysis…
• For EQ also always include condensation analysis….as you have already completed…
• After you have completed review and highlighted issues, please re-do your thermal report using this example as a concept to see what your conclusion/s are….