'>The FID for this project will be most likely postponed by 1 year.
- FID : Jan2017
- award EPCI and issue LOA : Sept 2015- maintain
- EPC prepare detail engineering and bid long lead item : 12 months after receiving LOA by reducing number of man hours, Sept 2016 - engineering and bid for long lead should be ready but cannot issue PO till Jan2017 when the FID would be approved. (Update June 2015)
'> Internal Technical recommendation for EPC : by Mar 20 2015
Internal commercial recommendation for EPC: by mid-April 2015
Project Schedule; original plan
1) Early Engineering budget : starting from Sept 2015
a. Chevron will issue LOA to EPC and start engineering by Sept 2015
2) FID to award : Dec 2015
(Updated March 2015)
> Short List Samsung Daewoo (updated March 2015)