I was discussing this plan with Mr. Anant and understand from him that apart from the first PO material of 913 MT, S and L should also have another around 600 MT already lying at the warehouse. Which means that we should be lifting that much material from the warehouse on an immediate basis and rest from the plant (from online production). We need you to check with S and L on the same and provide us with an exact visibility of the cargo available and the planning.