ATTN : K.Chat , K.Talit
As you know already we plan to pouring concrete for the wall first layer of primary digester 041 on Monday 2015.
I’d like to recommend to you again what you must to do and preparing before concrete placement.
1.) Recheck the covering around tank and put more spacer somewhere .( I tell to K.Talit already this morning)
2.) Move out some rebar in the formwork. .( I tell to K.Talit already this morning)
3.) Backfill cement mortar in the hole between bottom of formwork and the floor. .( I tell to K.Talit already this morning)
4.) Prepare vibrator 8 Pcs. ( I tell to K.Talit already this morning)
5.) Prepare Sika Rugasol C for make the connection joint of concrete. .( I tell to K.Talit already this morning)
6.) Prepare water jet high pressure.
7.) Prepare good man power to do this job.
8.) Prepare sprayer for spray Sika Rugasol C. .( I tell to K.Talit already this morning)
If you have some clarification don’t hesitate to call me.