The 1st phase valve are not install insulation yet need to finish also but not additional work. The repair insulation in case of installation team, we request you repair with additional charge with report sign from our engineer.
For 2nd phase follow unit rate of 1st phase.
Better you team discussion with me on site.
Thank you & Brgs.