(l) Decommissioning liabilities included in the cost of property, plant and
equipment
Paragraph 17.10(c) states that the cost of an item of property, plant and
equipment includes the initial estimate of the costs of dismantling and removing
the item and restoring the site on which it is located, the obligation for which an
entity incurs either when the item is acquired or as a consequence of having used
the item during a particular period for purposes other than to produce inventories
during that period. A first-time adopter may elect to measure this component of the cost of an item of property, plant and equipment at the date of transition to this
FRS, rather than on the date(s) when the obligation initially arose.