A factory is engaged in assembly production of product P that consists of components
A and B.
The processing of component A requires component C
, and the processing period is one week
. The delivery lead times of purchased components B and C are
two weeks and three weeks, respectively
. Product P can be assembled in one week
only after components A and B are both delivered.
What is the minimum number of
weeks required to produce one unit of product P, including the delivery periods of the
components? Here, there is no stock of any of the components.
a) 4 b) 5 c) 6 d) 7