As per Project A, the final step in the analysis was to develop treatment plans for the major risks identified above and then revise the RS and RPN by acting on those treatment plans. Therefore, the RS and RPN values of all project risks were revised based on having effected their treatment plans. The result of this was that the RS and RPN values of all of risks were below their respective critical values. This is depicted by the empty top right-hand quadrant in the scatter diagram, which demonstrates that all of the critical risks have been mitigated.