[D] We need a room for store disassembled parts of each vehicles "We need a room for store disassembled parts of each vehicles
near the working bay. *" "This room should be build at the back side of the work shop along the wall.
We will discuss and consider about this matter with APPS and P. Color on 14th Oct.
This is an item which APPS considered as additional construction but I think
they won't ask for large amount of additional cost because 6 Ventilations
are deleted from their previous quotation.(Requested by P Colors)
Waiting information of necessary size from P Colors→ Fill out temporary
size on sheet ""caption (E) Part2""
We'll inform APPS after we found out necessary size.
"
[E] We should install odor prevention measure to the exhaust unit. "We should install odor prevention measure to the exhaust unit.
" "We would like to purchase from BANZAI.
Their quotation will be 146,000 THB (we will have 15% discount)= 124,100 THB
Please order to Banzai.(Requested by P Colors)
We need to import this item from Italy so please place an order within next week at latest.
"