Hi Vasit,
For the second point for the staff house I am agree with you . Building permit for phase 2 and my payment for the voice are required. I am always in business don't worry.
But for the first issue I cannot accept your conditions for some raisons
1 you were out of delay for your work in your contract you write 2 at 4 months depending of the complexity now we are more than 1 year.
2) these delay cost to me . In fact the price for some presentations increase already 20000 baths more because you were late
3 you never send to be design 5 I have only desidn 4 3. D we already told you that we don t like your roof . You need a long time to modify something . I don't count how many email I had to send to but it is not normal between customer and his architect. My time is also money.
4 since the contract signature , you were not available for this contract . It was not priority and each time it was so difficult to have a meeting with you.
Also I think it could be with this new roof to forget these problems and finish good our contract and don t ask money for that
I hope your understand too your interest to close friendly this contract.
Best regards
patrick