Hi Waranthaporn,
After 2nd thought, I think it maybe making sense for the 114 days production lead time TTM advised for the current PO placed but I need extra information in order to explain to the GR team.
1) How long does the factory closed for the CNY holiday in Thailand?
2) Sharpener – Are you importing it from China and then assembly upon receipt at the factory? What is the normal production lead time and shipment lead time for the sharpener if so?
3) For items with pencils only, if we can work with the below proposals, can we keep the production lead-time at 90 days as the MOQ issue should have been resolved.
4) For the pencils, what is the minimum production qtys that MUST be put in the production lines for each type of pencils?
Below are the proposals selected based on the feedback of TTM, please confirm that these qtys are the PO qtys needed, but the packaging qtys that will be produced. Our understanding is that TTM can hold on to the packaging to use for orders for the remainder of the year. Please confirm that this is correct.
• ORDER ADDTN’L 20K OF BAGS FOR 7CT (100498) ( THIS WOULD BE USED IN DEC/FEB TIMEFRAME)
> MOQ requested in tracker is 10,032
> Proposals 1: Best MOQ 50K for the bag with cost increase from $0.343 to $0.35 (3% increase) as the printer does not accept the MOQ of 20K
=> So TTM is going to order 50K bags from your printer in 1 time, correct? What is the minimum qty that Meijer has to put on each PO? Can TTM keep the packaging stock for Meijer until they are all consumed? Can we place a PO with qty around 10K or 20K per PO? And place more PO’s at a later time of the year for using up the stocks purchased? Please advise what can be done.
• ORDER ADDTN’L 15K FOR 4CT JUMBO( PID 92527) 10K FOR DELIVERY LATE JULY/EARLY AUGUST, 5K DEC DELIVERY
> PO#205439026 issued to TTM, qtys 10,008pcs with ship date 5 July: delivery for late July / early August above
> MOQ requested in sample tracker 3,600pcs
> Proposal 2: Meijer commit to 20K of blister & blister card and cost will be kept at $0.585
=> So TTM is going to order 20K blister & blister cards from your printer in 1 time, correct? What is the minimum qty that Meijer has to put on each PO? Can TTM keep the packaging stock for Meijer until they are all consumed? Can we place a PO with qty less than 10K per PO? And place more PO’s at a later time of the year for using up the stocks purchased? Please advise what can be done.
• ORDER ADDTN’L 10K FOR 50CT (PID 101095) FOR DELIVERY LATE JULY/EARLY AUGUST
> PO#205439026 has already been issued to TTM with qtys 10,032pcs with ship date 5 July which should be the same as the delivery late July / early August above, please advise if otherwise.
> MOQ requested in sample tracker 4,032pcs
> Proposals 1: Best MOQ 10K with cost increase from $2.64 to $2.672 (1.2% increase)
=> So TTM is going to order 10K blister & blister cards from your printer in 1 time, correct? What is the minimum qty that Meijer has to put on each PO? Can TTM keep the packaging stock for Meijer until they are all consumed? Can we place a PO with qty less than 10K per PO? And place more PO’s at a later time of the year for using up the stocks purchased? Please advise what can be done.
• ORDER ADDTN’L 10K FOR 24CT ( PID 3304234) FOR DELIVERY LATE JULY/EARLY AUGUST
*****RE: TTM AN MOQ REQUEST FOR THE 24 COUNT WAS MISSED ON THE REQUEST I SENT: 20K MOQ IS TOO HIGH, PLEASE REQUEST THESE TO BE LOWERED TO 5-6K!!!
> PO#205439026 has already been issued to TTM with qtys 10,080pcs with ship date 5 July which should be the same as the delivery late July / early August above, please advise if otherwise.
> Proposal 2: Meijer commit to 20K of paper box and cost will be kept at $1.05
=> So TTM is going to order 20K paper box from your printer in 1 time, correct? What is the minimum qty that Meijer has to put on each PO? Can TTM keep the packaging stock for Meijer until they are all consumed? Can we place a PO with qty less than 10K per PO? And place more PO’s at a later time of the year for using up the stocks purchased? Please advise what can be done.
Please advise if the above can solve the MOQ issue that we are facing and that if we can get you the order confirmation for PO#205439026 lastest by 4/10 (next Friday), can the ship date of 7/30 be met?
Please try your best to get back to us as much info as you can before end of today as the GR team and HK office will be closed for tomorrow and won’t be back until next Wed (4/8). Thanks!
Hi Waranthaporn,
After 2nd thought, I think it maybe making sense for the 114 days production lead time TTM advised for the current PO placed but I need extra information in order to explain to the GR team.
1) How long does the factory closed for the CNY holiday in Thailand?
2) Sharpener – Are you importing it from China and then assembly upon receipt at the factory? What is the normal production lead time and shipment lead time for the sharpener if so?
3) For items with pencils only, if we can work with the below proposals, can we keep the production lead-time at 90 days as the MOQ issue should have been resolved.
4) For the pencils, what is the minimum production qtys that MUST be put in the production lines for each type of pencils?
Below are the proposals selected based on the feedback of TTM, please confirm that these qtys are the PO qtys needed, but the packaging qtys that will be produced. Our understanding is that TTM can hold on to the packaging to use for orders for the remainder of the year. Please confirm that this is correct.
• ORDER ADDTN’L 20K OF BAGS FOR 7CT (100498) ( THIS WOULD BE USED IN DEC/FEB TIMEFRAME)
> MOQ requested in tracker is 10,032
> Proposals 1: Best MOQ 50K for the bag with cost increase from $0.343 to $0.35 (3% increase) as the printer does not accept the MOQ of 20K
=> So TTM is going to order 50K bags from your printer in 1 time, correct? What is the minimum qty that Meijer has to put on each PO? Can TTM keep the packaging stock for Meijer until they are all consumed? Can we place a PO with qty around 10K or 20K per PO? And place more PO’s at a later time of the year for using up the stocks purchased? Please advise what can be done.
• ORDER ADDTN’L 15K FOR 4CT JUMBO( PID 92527) 10K FOR DELIVERY LATE JULY/EARLY AUGUST, 5K DEC DELIVERY
> PO#205439026 issued to TTM, qtys 10,008pcs with ship date 5 July: delivery for late July / early August above
> MOQ requested in sample tracker 3,600pcs
> Proposal 2: Meijer commit to 20K of blister & blister card and cost will be kept at $0.585
=> So TTM is going to order 20K blister & blister cards from your printer in 1 time, correct? What is the minimum qty that Meijer has to put on each PO? Can TTM keep the packaging stock for Meijer until they are all consumed? Can we place a PO with qty less than 10K per PO? And place more PO’s at a later time of the year for using up the stocks purchased? Please advise what can be done.
• ORDER ADDTN’L 10K FOR 50CT (PID 101095) FOR DELIVERY LATE JULY/EARLY AUGUST
> PO#205439026 has already been issued to TTM with qtys 10,032pcs with ship date 5 July which should be the same as the delivery late July / early August above, please advise if otherwise.
> MOQ requested in sample tracker 4,032pcs
> Proposals 1: Best MOQ 10K with cost increase from $2.64 to $2.672 (1.2% increase)
=> So TTM is going to order 10K blister & blister cards from your printer in 1 time, correct? What is the minimum qty that Meijer has to put on each PO? Can TTM keep the packaging stock for Meijer until they are all consumed? Can we place a PO with qty less than 10K per PO? And place more PO’s at a later time of the year for using up the stocks purchased? Please advise what can be done.
• ORDER ADDTN’L 10K FOR 24CT ( PID 3304234) FOR DELIVERY LATE JULY/EARLY AUGUST
*****RE: TTM AN MOQ REQUEST FOR THE 24 COUNT WAS MISSED ON THE REQUEST I SENT: 20K MOQ IS TOO HIGH, PLEASE REQUEST THESE TO BE LOWERED TO 5-6K!!!
> PO#205439026 has already been issued to TTM with qtys 10,080pcs with ship date 5 July which should be the same as the delivery late July / early August above, please advise if otherwise.
> Proposal 2: Meijer commit to 20K of paper box and cost will be kept at $1.05
=> So TTM is going to order 20K paper box from your printer in 1 time, correct? What is the minimum qty that Meijer has to put on each PO? Can TTM keep the packaging stock for Meijer until they are all consumed? Can we place a PO with qty less than 10K per PO? And place more PO’s at a later time of the year for using up the stocks purchased? Please advise what can be done.
Please advise if the above can solve the MOQ issue that we are facing and that if we can get you the order confirmation for PO#205439026 lastest by 4/10 (next Friday), can the ship date of 7/30 be met?
Please try your best to get back to us as much info as you can before end of today as the GR team and HK office will be closed for tomorrow and won’t be back until next Wed (4/8). Thanks!