Dear all,
Pls see tasks schedule for PPD staff sales as following. I propose to have staff sales on Apr 24th – 25th . If you have any comments, pls let me know ka.
Apr 9 : DP submit product list to MKT.
Apr 11 : MKT & controller confirm staff sales list back to DP & WH with discount price. (WH will consider stock volume and will confirm date & time to deliver stock to office 9th fl.)
Apr 16 : K Anya approval.
Apr 17 – 18 : MKT create presentation for internal PR.
Apr 21 : Controller organize cashier process and provide list of products with barcode and discount price for cashier set up to supplier.
Apr 23 : WH deliver stock to office.
Apr 24 – 25 : PPD staff sales on 9th fl.
Apr 28 : Controller reconcile stock with actual sales.
Apr 29 : Customer service key in actual sales in to SAP.