A zero time-lag implies that the second activity j can start immediately after the
finish of the first activity i , or later. It does not force the immediate start after the
finish of the first activity, since the definition phase only describes the technological
requirements and limitations and does not aim at the construction of a timetable.
A finish-start relation with a nonzero time-lag can be represented as follows: