Dear Khun Thalit,
As we discussed yesterday, the 9th of March 2015 at Sebigas UAC site’s office in Khon Kaen – Phu Pha Man District (attached you can find the email sent after the meeting summarizing what we talked for), below you can find my answer to your letter CNS_PPM2/001, following your points:
1) If CNS followed the schedule attached at the agreement, CNS would not waste one month with the poles repairing, in fact the poles to repair in the tank 041 were just 7. CNS wasted about 1 month because CNS did not follow the time schedule and also my continue solicit to respect the time schedule (attached you can find some of the emails sent);
2) The concrete plant is a CNS subcontractor and SebigasUAC cannot be responsible of CNS subcontractor’s problems or delay;
3) SebigasUAC stopped the work on 26th February 2015 for obvious reasons and also allowed to restart the work on 28th February 2015 (attached “20150228 - Re_ PPM2 - end of the civil work”).
Moreover, after our discussion of yesterday regarding the time schedule, I am here to tell you again that the time schedule you submitted to SebigasUAC is impossible to respect (go to see the attachments “20150309 - Rev.8 Schedule - Project Gantt” and “img-150310023317”).
The minimum time to complete the whole work is about 4 months since today.
Attached you can find the main emails sent to CNS.
Thank you and best regards
Alessandro Cossa