Dear Sirs,
In case of my resignation immediately, I've to apologize you that there are something have remained not clarified, then please let your team follow them as the following;
1. Remained / Issuing PO from customers
• TMT - Modified ClampLock the last updated Mr Narupon PEN said to me that they tried to push their PR via the Oracle system twice, but it couldn't access. Then he will set up the internal meeting with TMAP-EM purchasing again.
• TMT - M5 (special) Mr Chaiwat POB requested one more prototype of the last updated design, which will be delivered to him within this week. And he remained not let us cut order without PDS cancellation for last 4 units delivered to him.
• TMAP-EM - Prototype SKD/Modified Clamplock/Remarking Barcode these items Mr Panyawat will follow and issue for us but we need to follow the output conclusion with Mr Nuttapoom and let him issue PR for remarking barcode.
• HMMT - Follow Ms Natchawan for their price increasing allowance.
2. Incoming new projects from customers
• TMAP-EM - They have planned to start trial POLYGON System on this March 15 '2013. By the way, I've tried to cut this process not related to Sales responsibilities after they launch the system by let our IT takes care for the system and MFG takes care for their operational.
• STM - The R/Dunnage will be arrival in this week as their E.T.A., which they have totally 90 modules from 6 containers. And Mr Adsawin, engineer from STM, will visit and take the observation for this matter when they are devanning.
• The critical point is seemed we got the invisible cost added up as we need to spend the more area and store them at TK as their returning volume is greater than their estimated.
• But Mr Adsawin said he will review the price for the incoming AR in April '2013.