ase see attached for ECB lighting for the ceiling grid works. Kindly be advised of the following;
- The lighting layout dimensions are not definite. We can only know the estimated number of lighting within the area. Lighting can only be fully installed after surrounding grids are completed. We shall try our best to minimize re-works.
- The switch box, and electrical conduits shall be embedded into the walls, for both 1F and 2F. We are still in the midst of proposing exposed electrical conduits at the cable floor. I shall inform you when EGAT confirms.
- HVAC drawings are available. I shall forward you the drawings in a separate email. You can use the drawings as a confirmation to proceed block work.
If any questions, feel free to see me directly.