(c) If the Supplier fails to Commission the Project by the Completion Date, then liquidated damages in the amount of THB10,000 per week will be assessed for every day the Supplier delays Commissioning beyond the Completion Date (if the delay is caused by the Supplier without the default of Suretex), up to a maximum of 10% of the total Project Cost. It being practically impossible to calculate the loss to Suretex caused by such delay, this provision for liquidated damages represents the best estimate of Suretex and the Supplier of loss likely to be suffered by Suretex due to failure to complete the Project on time, and shall not be, or be deemed to be a penalty or forfeiture. Suretex may, without prejudice to any other method of recovery, deduct the amount of any compensation under this clause from any monies due or which may become due to the Supplier.