By March 2010, the concrete core was rising steadily at approximately 3 metres a day. After a pause in March–April 2010, it continued rising, reaching the 33rd floor in mid-June, almost level with the top of Guy's Hospital, which stands at 143 metres On 27 July 2010, the core stopped rising, having reached the 38th floor, and was reconfigured for further construction.