It is also noted that NO steelworks have commenced at the 10th floor area, and that this is also considered to be in delay, again the glass panels are available and are pending delivery to the project site, furthermore and in addition the aluminum cladding has not yet been delivered, hence both the 9th and 10th floor glazed balustrade works are now all well behind schedule.