2. The measure for correction.
2.1 The responsibilities and the penalties. (from the meeting on 04/04/2014)
a) In case of the construction equipment suppliers does not send “the transportation permits
to Khanom Power plant” to the drivers.
This case is Onshore Consortium’s responsibilities.
b) In case of the drivers don’t follow the regulation
The staffs at the fort can hold “the transportation permits to Khanom Power plant” from the
driver and can stop that transportation, for the safety reasons.
If there are the complaint from the communities about the truck’s drivers. Owner can revocation
of “the transportation permits to Khanom Power plant” from Onshore Consortium.
(Can be direct complain to Consortium teams or to the EGCO staffs or the join audit team)
The delay of the transportation which caused by the complaint from the community about
transportation safety is the Onshore Consortium’s responsibilities.