In the absence of a fixed price for varied work being agree between the parties, varied work shall be measured and valued for payment in accordance with this Clause
Whenever the Project Director requires any part of works to be measured, the Project Director shall give reasonable notice to the Contractor' s Representation, who shall
promptly either attend or send another qualified representative to assist the Project Director in making the measurement and
supply any particulars requested by Project Director
If the contractor fails to attend or send another qualified representative the measurement made by (or on behalf of) the Project Director shall be accepted as accurate
Except as otherwise started in the Contract wherever any varied Works are to be measured from records, these shall be prepared by the Project Director. The Contractor shall, as and when requested, attend to examine and agree the records with the Project Director, and shall sign the same when agreed. If the Contractor does not attend the records shall be accepted as accurate.
If the Contractor examines and disagrees the records, and/or does not sign them as agree then the Contractor shall give notice to the Project Director of the respects in which the records are asserted to be inaccurate. After receiving this notice, the Project Director shall review the records and either confirm or vary them. If the Contractor does not so give notice to the Project Director within 14 days after being requested to examine the records, they shall be accepted as accurate