Dear Planner/Warehouse owner,
Please pay attention more one NB/EeePad/MB/VGA buffer fulfillment.
We still face to part shortage issue, especially MB/VGA.
By the way, we have difficulty to co-work with CHUB(Arvato) because there is no one could reply CSM team or ASP/RSP any logistic issue.
It effects buffer shipment no matter inbound or out bound.
Already more than 3 months and Thailand buffer fulfill rate become worst, please speed up to solve the problem.
If possible, please sync issue with logistic internal due to some of problems are not ASP/RSP receive delay. Most of problems are CHUB parts discrepancy.
Drag the longer the situation worse.
Thank you.