Liquidates damages for delayed delivery shall be 0.5 per cent for
every completed week’s delay (fraction of the week shall be
prorated) and shall in no case whatsoever altogether exceed 5 percent of the Contract price of the part on which such liability is based. No damages at all shall be due for the first two weeks of
delay. In case of short shipped parts, Purchaser shall advise ABB
within 7 days from delivery date or within 21 days from ABB
submission of shipping documents to the Purchaser. Otherwise it
shall be deemed that a claim is waived and Purchaser is not
entitled to any liquidated damages for delay.