This method works when a project is open, but data files are not imported yet. In this case, do the
following steps:
1. Select Properties item from the Project menu or click on the toolbar. The Project
properties dialog window opens.
2. Open the Fiducial points tab to copy the desired fiducial points from the Justin database to
the project. It allows snapping sites to the fiducial points.
3. Select the Scenario tab.
4. Select the Processing and Adjustment check boxes.
5. Click OK. Justin implements the adjustment automatically when the file import has been
completed successfully.
6. Select the Adjustment tab of the Project pane to check the adjustment process is over.
Justin uses the following adjustment parameters by default (see “Setting Adjustment Parameters”
for detailed information about adjustment parameters):