5. Planning (continued…/…)
-Review alternatives
-Construction Programme
-3 month Stage programme
-Select activities for report of ‘Progress against Programme’
-Resource schedules
-Plant
-Labour
-Materials
-Subcontractors
-Staff
-Temporary Works
-Overall site layout
-Information Schedule
-Purchasing Programme
-Design Office Programme
-Progress Payment Schedule
-Project Quality Plan (‘QA’
Contract)
6. Cost Control
-Notification (internal) of new
Contract award
-Prepare allowances from tender (particularly for procurement)
-Issue Handover Package
7. Contract Documents/Drawings
-Obtain. No. copies and distribute to…
8. Staff
-Issue schedule to H.O.
-Availability of staff from other contracts/offices
-Recruitment
-Terms and conditions
-Job descriptions
-Interviews
-Vehicle policy
-Temporary accommodation
-Issue organization chart internally
-Budget for staff expenses
9. Plant
-Issue schedule to SCM/Plant Department
-Obtain list of plant available
-Check local hire rates