Activity 1 can be done right at the start. When this is finished both activities 2 and 3 can
start. Activity 4 can be done after both activities 2 and 3, and so on. Continuing with this
logic gives the diagram shown in Figure 8.8. When we have drawn this network, we can
start looking for improvements