Primary activity rates are computed by dividing the budgeted activity costs by practical
activity capacity, where activity capacity is the amount of activity output (as measured
by the activity driver). Practical capacity is the activity output that can be produced if
the activity is performed efficiently. Using data from Exhibits 4-13 and 4-14, the activity
rates for the cardiology unit nursing care example can now be calculated